Senate probe sought on delays in NGCP projects听听

A SENATOR has filed a resolution seeking to investigate the delayed projects of transmission operator National Grid Corporation of the Philippines (NGCP).听
Senator Sherwin T. Gatchalian said on Sunday that only 37.5% or six out of 16 power transmission projects considered to be 鈥Energy Projects of National Significance鈥 have been completed.听听
鈥When we talk about attracting investments into the country, the power supply is a fundamental consideration. How can we attract investors if we don鈥t have adequate supply and if it鈥s too costly?鈥 Mr. Gatchalian said in a statement.听听
He also said in Senate Resolution No. 616 that the delay has also led to the 鈥congestion of the grid.鈥听
He cited among other projects the Hermosa-San Jose 500kV Transmission Line, which was supposed to be completed in December 2020 but was extended until July, and the Cebu-Negros-Panay 230 kV Backbone Stage 3 Project that was targeted for completion in Dec. 2020 but was moved to August 2023.听听
鈥Although these projects are delayed, they are already part of the transmission charge being collected by the NGCP pursuant to its 2020 approved interim maximum annual revenue,鈥 Mr. Gatchalian said.听听
Congress has been studying proposals for the government to regain full ownership of the NGCP, citing the private firm鈥s inability to provide a stable power source to the public. It has also raised concerns on foreign ownership of the corporation, which poses a security threat to the country.听
鈥As the sole backbone for the transmission of electricity throughout the country, the NGCP is duty bound in ensuring that it is able to adequately serve generation companies, distribution utilities, and suppliers requiring transmission and ancillary services through transmission system,鈥 Mr. Gatchalian said. 鈥 Beatriz Marie D. Cruz