THE Department of Public Works and Highways (DPWH) said Wednesday that the P1.46-billion Estrella-Pantaleon Bridge project connecting Makati City and Mandaluyong City is expected to be completed in the second quarter.
In a statement, Public Works and Highways Secretary Mark A. Villar said that motorists will be able to use the widened and modernized bridge in the 鈥渟econd quarter of 2021.鈥
The Chinese-funded project is now 72% complete and is 8% ahead of schedule, the department added.
The project is part of the government鈥檚 EDSA decongestion program.
鈥淒esigned to decongest Guadalupe Bridge along EDSA, the main bridge of Estrella Pantaleon is a 146.0-meter prestressed concrete girder bridge with V-shaped piers, while the approach bridge/viaduct is a 66.0-meter prestressed continuous girder bridge. The approach roads at both sides have a length of 294.46 meters,鈥 the DPWH said.
The DPWH announced in January 2019 that it would close the old Estrella-Pantaleon Bridge for 30 months for 鈥渄emolition and reconstruction.鈥
The project is among the 14 agreements signed during Chinese Premier Li Keqiang鈥檚 state visit to Manila in November 2017. 鈥 Arjay L. Balinbin