THE National Grid Corp. of the Philippines (NGCP) said it is seeking an 鈥渦rgent resolution鈥 from the Supreme Court (SC) of a temporary restraining order (TRO) that blocked it from working on a site needed for its Panay-Guimaras 138-kilovolt interconnection project.

鈥淲e are hopeful for the urgent resolution of the issue so as not to hamper the interconnection which will improve the region鈥檚 power transmission line projects,鈥 the NGCP said in a statement on Thursday.

The SC had granted the petition of the Iloilo Grain Complex Corp. (IGCC) for Certiorari and Prohibition with Very Urgent Application for Temporary Restraining Order and/or Writ of Preliminary Injunction.

IGCC owns the property where two towers are set to be erected. The NGCP said the site is 鈥渃rucial as this 1.7-kilometer transmission line will connect the proposed Iloilo Substation to the Ingore Cable Terminal Station.鈥

The cable terminal station will serve as the connection point of the submarine cable to Guimaras Island.

The NGCP filed an expropriation case on Sept. 30, 2022 to acquire the property, which was approved by Iloilo Regional Trial Court (RTC) Branch 33 on Nov. 3, 2022.

A writ of possession was then issued on Dec. 12, 2022, but the IGCC submitted a motion for reconsideration on Jan. 18, which was denied by the RTC.

The dispute was then elevated to the SC, which granted the TRO.

The NGCP said that the TRO prevents it from carrying out a component of the project crucial to linking the two islands.

鈥淭he Supreme Court鈥檚 decision is disheartening as it hinders us from fulfilling our commitment to the residents of the islands of Panay and Guimaras, including fast-developing Iloilo City,鈥 the NGCP said.

鈥淣evertheless, we steadfastly maintain our dedication to enhancing power transmission within the area despite this setback,鈥 it added.

The interconnection project is an upgrade of the existing submarine cable connecting Panay and Guimaras. It is targeted to be completed in December next year.

The NGCP said it continues to seek 鈥渁n expeditious and amicable settlement鈥 with the landowner. However, the grid operator said that it is reluctant to move forward with IGCC鈥檚 proposal, which involves a reroute through a residential area affecting five households.

鈥淲hen we plot the route of our transmission line projects, a major consideration is the existence of structures and residents. We aim to traverse areas that will cause least destruction to property, and result in the least number of persons displaced,鈥 it added.

According to the grid operator, 鈥渁ny deviation in the established route may also affect adjacent towers and cause further delay to the completion of the project.鈥 鈥 Sheldeen Joy Talavera